Supreme Court Erases Legal Cavity in Section 37 Appeals under Arbitration Act

On 19 March 2021, A three-judge bench of Justices RF Nariman, BR Gavai, and Hrishikesh Roy, in the case of Government Of Maharashtra Vs Borse Brothers Engineersc Pvt. Ltd explicated the law regarding condonation of delay in filing of appeals falling under section 37 of the Arbitration and Conciliation Act, 1996.

Overturning its earlier decision in the case of N.V International Vs State of Assam, the court said that the very foundation of the judgment in N.V International was ‘erroneous in law’. The court criticized the judgment in N.V. International for failing to recognize that the issue fell under the purview of the Commercial Courts Act.

Arbitration Law

Stating that the line between interpretation and legislation can be blurry at times since it has been consistently held that judges do more than interpret the law; they also establish it.

The court examined the conflicting provisions of the Arbitration and Conciliation Act, the Commercial Courts Act, and the Limitations Act. Seeking to contrive a harmonious interpretation of the provisions of the concerned statutes, the Apex Court stated that the provisions of one section of the statute cannot be used to contradict those of another unless it is impossible to effect a reconciliation between them. The court also opined on the limit of judicial intervention and stated that extraneous meddling of the court in matters that don’t merit its perusal could amount to judicial legislation. Overturning the judgment in N.V. International, the court allowed condonation of ‘short’ delays insofar as such action was not prejudicial to the opposite party and the delay wasn’t a result of negligence.

In its findings, the bench expressed that the objective and spirit of the provisions of the Arbitration and Conciliation Act was to ensure speedy disposal of the matters.

Constructively analyzing the applicability of separate provisions along with the definition of ‘specified value’, the supreme court laid down specific guiding principles for posterity.

  1. If the subject matter in an appeal under Section 37 is less than the Specified Value (3 Lakh rupees), Article 116 or Article 117 of the Limitation Act will apply, which specify a 90-day or 30-day limitation period depending on whether the appeal is from a lower court to the high court or an intra-high court appeal.
  2. If the subject matter in an appeal under Section 37 is more than the specified value, the Limitation period of 60 days specified in section 13(1A) of the commercial court Act would be applicable.

The Supreme court also confirmed that Section 5 of the Limitation Act would apply to the above-mentioned appeals, both by virtue of section 43 of the Arbitration Act and by virtue of section 29(2) of the Limitation Act.

Counsel for Borse Brothers Engineers (respondent) argued that with respect to the objective of speedy resolutions under the Commercial Courts Act, Section 13 of the CC Act excluded the applicability of section 5 of the Limitation Act.

The court delved deeply into the supposed exclusion of the provisions of the Limitation Act by scheme of Commercial Courts Act. Section 13(1A) of the Commercial Courts Act only provided for a Limitation of 60 days from the date of the judgment, without elucidating on condonation of any delay beyond the specified period.

It drew a contrast between section 13 of the commercial court Act and section 16 read with Schedule thereof and the amendment made to Order VIII Rule 1 of CPC. A careful scrutinization of section 16 and the supplementary CPC provisions made it clear that the defendant in a suit is given 30 days to file a written statement, such period cannot be extended beyond 120 days from the date of serving of the summons; and upon expiration of the aforementioned term, the defendant forfeits the right to file a written statement, and the court cannot allow the written statement to be taken into consideration. The court pointed out the absence of any such provision in section 13 (which only provided an immediate period of filing the appeal), or any other section of the Commercial Courts Act.

Section 21 of the Act was also addressed, where the court held that the non-obstante clause contained in the provision could not be considered to override the Limitation Act. Therefore, the applicability of section 5 of the Limitation Act could be excluded by the scheme of the Commercial Courts Act.

Conclusion

Expounding on the scope for condoning delays, the Apex Court undisguised the law and addressed the lacuna situated in such appeals. This inconsistency in law was not dealt with in various iterations of judicial decisions interpreting the Limitation period for appeals arising out of section 37.

The bench reiterated the following principles to distinguish when a condonation of delay was merited and when one was not.

  • The Actions of the parties seeking delay must be bona fide and devoid of any negligence.
  • The condonation of delay must not be at the expense of the other party and must not cause any disbenefit to them.

The position on appeals remains unclear even after this ruling. The Court has simply made broad remarks in favor of applying Section 5 of the Limitation Act to section 37 appeals without presenting any convincing reasons for doing so, and the judicial precedents relied on by the Court were also of no substantive assistance. It’s worth noting that the Court hasn’t provided a single positive rationale for applying section 5 of the Limitation Act to section 37 appeals filed under section 13(1A) of the Commercial Courts Act for claims worth more than INR three lakhs, and the Court’s entire rationale in favor of condonation of delay is based on the Court’s negative comparison with other provisions under the Code of Civil Procedure. This, by itself, cannot be considered a sufficient and compelling basis to excuse the delay. Simply because the bench had the power to overrule the N.V. International ruling does not mean it was warranted in doing so without articulating a compelling reason for doing so.

The Court emphasized the sufficient cause’ theory to qualify such applications in its patchwork attempt to limit the inflow of condonation of delay applications that the courts will have to deal with in light of the floodgates that the Court had opened by its ruling. Despite the Court’s citation of previous precedents interpreting the phrase ‘sufficient cause,’ the standard still has a lot of room for interpretation. The authority to forgive fundamentally remains discretionary, leaving it up to the courts to determine based on the facts and circumstances of each case. In light of both the legislative void and the Borse Brothers Eng. decision, would be worth the legislature’s and the Supreme Court’s consideration, respectively.

Author: Sehaj Mahajan – a student of Bharati Vidyapeeth University (New Delhi), an intern at Khurana & Khurana, Advocates and IP Attorney,  in case of any queries please contact/write back to us via email vidushi@khuranaandkhurana.com

Leave a Reply

Categories

Archives

  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014
  • February 2014
  • January 2014
  • December 2013
  • November 2013
  • October 2013
  • September 2013
  • August 2013
  • July 2013
  • June 2013
  • May 2013
  • April 2013
  • March 2013
  • February 2013
  • January 2013
  • December 2012
  • November 2012
  • September 2012
  • August 2012
  • July 2012
  • June 2012
  • May 2012
  • April 2012
  • March 2012
  • February 2012
  • January 2012
  • December 2011
  • November 2011
  • October 2011
  • September 2011
  • August 2011
  • July 2011
  • June 2011
  • May 2011
  • April 2011
  • March 2011
  • February 2011
  • January 2011
  • December 2010
  • September 2010
  • July 2010
  • June 2010
  • May 2010
  • April 2010